Environmental Impact Assessment of GPP Operations in Pune: A Supreme Court Verdict

The case involving the Garbage Processing Plant operations in Pune has reached a significant milestone with the Supreme Court of India delivering a crucial verdict on the environmental impact assessment. This judgment will have far-reaching implications for waste management policies in the region. Stay informed as we delve into the details of this important legal battle.

Facts

  • The National Green Tribunal directed the Pune Municipal Corporation to close the Garbage Processing Plant operated by Noble Exchange Environment Solution Pune LLP at Baner, Pune.
  • The closure of the Garbage Processing Plant was ordered to be done within 4 months from the date of the Tribunal’s order.
  • The Tribunal granted the Maharashtra Pollution Control Board the liberty to recover environmental compensation from the Garbage Processing Plant based on the ‘polluter pays’ principle.
  • The environmental compensation was to be recovered for the entire period during which the environmental norms were violated by the Garbage Processing Plant.
  • The Municipal Corporation of Pune reserved land for a GPP in Baner Balewadi as per the Development Plan of 2002.
  • A Concession Agreement was entered into between the Municipal Corporation and the Concessionaire on 30 March 2015 for setting up an Organic Waste Processing Plant.
  • A Trust called Sus Road Baner Vikas Manch filed an OA in 2019 seeking to restrain the Concessionaire from operating the GPP due to procedural irregularities.
  • The Concession Agreement was for a period of 30 years.
  • The authorization granted by the MPCB for the GPP was renewed twice.

Also Read: High Court Misdirects in Proviso to Section 45 PMLA Case: Supreme Court Verdict

Arguments

  • The Solid Waste Management Rules, 2016 allowed a two-year period for migration and upgrading of the existing Plant to the 2016 Rules, with waste disposal provisions coming into force in April 2018.
  • The buffer zone requirements around waste processing and disposal facility came into force in 2017 and do not apply to a plant set up before that time.
  • The GPP’s location complies with the 2016 Rules as only waste from surrounding areas is processed there.
  • Efforts were made to find an alternative site but were unsuccessful due to various reasons.
  • The GPP was found to cause pollution, but corrective measures were being taken, including installing compactors to manage reject waste and generating raw biogas from slurry at a different site.
  • The MPCB’s circular dated September 6, 2021 clarifies certain positions regarding the operation and compliance of the GPP.
  • The OA filed challenging the Environmental Clearance (EC) was submitted much later than the renewal period, and the GPP authorization has been renewed till September 2025.
  • The GPP project aims to process food waste into biogas, which is used for clean public transportation in Pune City.
  • The Waste Segregation Unit operations are within city limits while the Processing Plant is situated outside the city limits.
  • Challenges to the GPP reservation in the Development Plan were not raised in the OA filed in March 2019.
  • The GPP processes waste in a manner beneficial for the environment by converting organic waste into usable biogas and organic manure.
  • MPCB followed the practice of only granting authorization before the circular dated 6 September 2021
  • Consent was granted for GPP on 1 November 2022 and again on 16 March 2024
  • Shri Laud proposed stringent directions to prevent pollution if GPP is allowed to continue operations

Also Read: Confirmation Dispute: Tripura University vs. Dr. Praveen Kumar Mishra

Analysis

  • The GPP has been reserved since 2002, and the land use plans confirm this.
  • The SEIAA granted Environment Clearance for the Organic Waste Management Plant after a public hearing in 2016.
  • The GPP and the Organic Waste Management Plant are part of the same Concession Agreement signed in 2015.
  • The Draft Development Plan reserved Plot No 48/2/1 for GPP, as per notifications.
  • The GPP closure would have adverse effects and inconvenience to the public due to waste transportation.
  • The 2016 Rules were notified in April 2016, and the GPP operations commenced before that.
  • The MPCB started granting consent for Solid Waste Management Facilities post-September 2021.
  • Various authorizations and clearances were obtained for GPP before the enforcement date of the 2016 Rules.
  • The term “things done” as interpreted by the court includes not only the actions taken but also the legal consequences that follow from those actions.
  • The term “anything duly done or suffered thereunder” in the law is aimed at ensuring that actions taken under a statute are not affected by its repeal.
  • The purpose of a saving clause in a statute is to protect actions taken under the repealed law.
  • The saving clause allows the pre-existing law to continue governing actions taken before the repeal comes into effect.
  • The Petitioner’s suggestion that the lives of slum rehab building residents can be endangered by the same staircase while prioritizing their members’ interest is not acceptable.
  • The High Court’s observations regarding the safety of the residents are agreed upon.
  • The impugned judgment and order of the Tribunal in OA No 210 of 2020 and Review Application No 49 of 2020 are quashed and set aside.
  • The appeals are allowed, and the OA of the Petitioner is to be dismissed.

Also Read: Supreme Court Judgement on SEBI’s Consent Order in Writ Petition

Decision

  • Plantation with thick density should be carried out around the GPP to create a green cover.
  • Consider growing Miyawaki forests in the Bio-diversity Park for green lungs.
  • NEERI to conduct environmental audits every six months for GPP, with strict compliance to suggestions.
  • Construct a shed to cover the reject area by December 31, 2024.
  • Take necessary steps to avoid foul odors affecting nearby residents.
  • Recommendations from NEERI include proper covering of slurry making area, installation of odor control systems, and slurry sampling and analysis for methane production.
  • Install portable compactors with hook mechanisms to prevent reject waste from touching the ground by December 31, 2024.
  • Construct bitumen road to Waste Segregation Plant and concrete the reject area for clean waste transfer and water accumulation prevention.

Case Title: PUNE MUNICIPAL CORPORATION Vs. SUS ROAD BANER VIKAS MANCH (2024 INSC 682)

Case Number: C.A. No.-000258-000259 – 2021

Click here to read/download original judgement

Leave a Reply

Your email address will not be published. Required fields are marked *