Remand for Reconsideration of Interim Compensation Amount in Environmental Case

As no reasons have been recorded for arriving at a figure of Rs.2,00,00,000/- (Rupees two crores), we propose to remand the case to the National Green Tribunal for reconsideration of the quantum of interim compensation amount payable by the appellant. Till the adjudication is made by the National Green Tribunal on the amount of interim compensation payable by the appellant, the sum of Rs.33,75,000/- (Rupees thirty three lakhs seventy five thousand) shall be treated as interim compensation.

Also Read: https://newslaw.in/supreme-court/supreme-court-ruling-section-34-ipc-applicable-in-brutal-murder-case-all-accused-held-liable/

Case Title: JAIPUR DEVELOPMENT AUTHORITY Vs. THE STATE OF RAJASTHAN (2023 INSC 700)

Case Number: C.A. No.-007018 / 2022

Click here to read/download original judgement